Past Updates

Updates

Week of 3/27
Crushing will be completed

Week of  3/26
Building pad excavation and preparation and rock crushing

Week of 3/19
Crushing will continue

Week of 3/12
Crushing will continue

Week of 3/4
Utilities start

Week of 2/27
Excavation of building footprint and rock crushing

Week of 2/20
Blasting completes, excavation of building footprint and rock crushing continues

Week of 2/13
Continue crushing, complete building pad excavation, start utility layout

Week of 2/6
Should complete blasting, continue crushing, excavate building pad

Week of 1/30
Hope to complete Blasting, finish site walls; start crushing operation; layout utilities

Week of 1/23
Continue Blasting; continue site walls, bring lower parking lot to subgrade

Week of 1/16
Blasting to continue; retaining walls to continue; rock crushing to start

Week of 1/9
Blasting to continue; retaining walls to continue; rock crushing to start

Week of 1/2
Blasting to continue; retaining walls to continue; rock crushing to start

Week of 11/21
Site wall construction  and blasthole borings to continue

Week of 11/14
Complete hauling away of surplus materials, start wall construction, start drilling for blast bore holes

Week of 11/4
Continue site wall installation. Start drilling to prep for blasting; blasting late in week; Complete removal of excess materials; Continue wall construction; Layout and drill bore holes for blasting;

Week of 10/31
Continuing to ram hoe loose rock; screen overburden and haul away excess

 


Progress Photos

As of March 23, 2017

As of March 10, 2017

As of March 6, 2017

As of February 16, 2017

As of February 8, 2017

As of January 31, 2017

As of January 21, 2017

As of 11/4

As of 10/28/16

 

© 2017 RCS Learning  All Rights Reserved.